Waterbabies Success Centre open 28th January 2012

Our visions of a better future are real; dreams do come true;
without that possibility,
nature would not incite us to have them...

                                                           John Updike

First_day_open__Jan_2012

OPEN 28th January... Bob Dunn in the carpark 

First_swim_Jan_2012

 

Kelly Rae taking the first dip

Jan 2012! 

  

 THE BUILDING YEAR 2011

See below

 

Blank-Canvas

     March 2011 Blank canvas ready to go!

 

Road-view

May 2011 Pool shells concreted, Office and changerooms underway 

 

June-2011-progress

 June 2011 Steel roof structure and pool posts craned in and more brick work goes up 

  

August-2011

July / August

After a lengthy standstill from all the much need rain we are back into it with the changerooms roof now on and curved steel up and ready to put the pool roof on.  

 

Mid-August

 August / September

The pool roofs are both on, pool plumbing is complete and we are getting ready to tile the pools and lay the slab around the pools. The office interior is now rendered ceilings and insulation will happen this week.

 Yahoo!!!

 

October_sand_carpark

  October sandpit car park 

 

Pool_1

 November 2011 POOL 1

  All we need is water

 

 finished_car_park

 December 2011 Car park finished

 

Kelly Rae and Bob Dunn

                                             